Skip To Main Content

Logo Image

Logo Title

Arrington Elementary

Project Description

Williamson County purchased property in the Triune area to build an elementary school to relieve overcrowding at schools in the eastern portion of the county. The property purchased includes enough space for both an elementary school and a future middle school. The architectural design follows the prototype utilized by the District since 2007 starting with Longview and Nolensville Elementary Schools and most recently with Creekside Elementary School. The school is a two-story building, with approximately 121,000 SF.

Location:

6280 Cox Road
Arrington, TN 37014

Key Dates:

  • Bids were opened on March 3, 2022, and a contract was awarded to Robert S. Biscan & Co.
  • The Notice to Proceed with construction was issued on April 15, 2022.
  • Construction is expected to be completed before July 2023 with the school becoming operational for the 2023-24 school year.
  • The State Fire Marshal issued a Certificate of Occupancy on August 10, 2023.
  • Staff and students are currently occupying the building and the contractor is completing punchlist items.

Architect drawing of school improvement

 

 

Front Elevation

A cleared construction site with dirt mounds in the foreground is bordered by green grass and trees, with houses visible in the distant background under a cloudy sky.
Construction is underway on a large building complex with a parking lot and equipment in the foreground, set against a backdrop of cleared land and distant green hills.
A new school building with a large parking lot in the foreground is surrounded by construction and undeveloped land in the background.
A newly constructed complex of brick buildings with parking lots in the foreground is surrounded by undeveloped land and distant houses in the background.
A large construction site with buildings and equipment in the foreground is surrounded by fields and a residential area in the background.
A large, dark-roofed building complex with a parking lot in the foreground is surrounded by construction sites and undeveloped land in the background.
A large, multi-story building under construction dominates the foreground, surrounded by dirt piles and construction equipment, while the background reveals agricultural fields and a few scattered houses.
ARES May 22
ARES Jan 23
ARES Nov 22
ARES March 2023
10 - August 2023
ARES June 2023
12 - October 2023

Monthly Progress Photos