Mill Creek Middle School Softball Field Project
Project Description:
Construction of a new softball field at Mill Creek, located south of the existing baseball field and north of the multipurpose field. The construction will be phased. Improvements will include fencing, infield, concrete work, dugouts, field lighting, and backstop.
Location:
200 York Trail
Nolensville, TN 37135
Key Dates:
- Phase 1 Construction included fencing, infield, concrete work, and temporary dugouts. Phase 1 was completed in July 2023 with the field ready for play for the 2024 softball season.
- Permanent dugouts were added during Phase 2 Construction in June 2024.
- Field lighting installation and backstop improvements were completed during Phase 3 Construction in February 2025.
- The softball field is complete and ready for play.