Page High School Phase III

Project Description:

The original construction of Page High School dates back to 1974 with multiple renovations and additions throughout the 1980s and 90s. This is the third phase of a four-phase recapitalization project to replace and expand the capacity of Page High School. Phase I improvements included infrastructure upgrades and turf replacement of the multi-purpose athletic field. Phase II construction added the first of two three-story buildings. The 102,000 Phase II building was completed in 2021. Phase III recapitalizes more classrooms, labs, offices, Kitchen/Cafeteria, Band, and JROTC areas. Phase III will construct a three-story building with approximately 101,000 SF.

Location:
6281 Arno Road
Franklin, TN 37064

Key Dates:

  • Bids were opened on November 4, 2021, and a contract was awarded to RG Anderson Company, Inc.
  • The Notice to Proceed with construction was issued on December 20, 2021.
  • Construction is expected to be completed before June 2023 with the school becoming operational for the 2023-24 school year.
  • The State Fire Marshal issued a Certificate of Occupancy on June 26, 2023.
  • Staff and students are currently occupying the building and the project is now Substantially Complete.

 